By Shannon Lukens.
Dust Suppression starts Monday, June 12. It’s a five-to-six week project with Routt County Road & Bridge. They’ll start in Hayden, move east to Steamboat Springs, then south to Oak Creek and finish north of Routt County Road 44. The schedule is on our website.
- Monday, June 12: CR 78, CR 78A, CR 76, and CR 74A
- Tuesday, June 13: CR76A, CR 80, CR 70, CR 51B. CR 69, United Pit, Hayden Water Treatment, CR 211, and CR 65
- Wednesday, June 14: CR53, CR 59, RB 8, RB 19, CR 55 and CR 29
- Thursday, June 15: CR 67, CR 53 and CR 37
Press Release from Routt County; June 9, 2023.
Dust Suppression Project to Begin Monday, June 12
Steamboat Springs, CO, June 9, 2023 – Routt County Road & Bridge Department will begin the annual Dust Suppression Project on Monday, June 12. This is a five to six week project, and they will start in Hayden, move east to Steamboat Springs, then south to Oak Creek and finish north of Routt County Road 44.
The daily schedule will be posted online at co.routt.co.us/374/Road-Work-Closures. This schedule will be updated Monday through Friday by 9:00 am. This schedule is subject to change due to weather or mechanical issues. The current schedule for next week has been updated online, and is listed below:
Monday, June 12: CR 78, CR 78A, CR 76, and CR 74A
Tuesday, June 13: CR76A, CR 80, CR 70, CR 51B. CR 69, United Pit, Hayden Water Treatment, CR 211, and CR 65
Wednesday, June 14: CR53, CR 59, RB 8, RB 19, CR 55 and CR 29
Thursday, June 15: CR 67, CR 53 and CR 37
It is recommended that you wash your car, including the undercarriage to remove any mag chloride residue.
###