By Shannon Lukens for Steamboat Radio News. Courtesy photo.
Milling has begun on city streets in the City of Steamboat Springs. It will last through May 27.
Then paving is happening May 18 through June 3.
Work is being done by United Companies and it is weather dependent.
Below is the tentative schedule. Flyers have been handed in the neighborhoods. This list will be updated if dates change.
Milling Schedule
- May 12-15 is Ridge Road, Storm Meadows Drive and Burgess Creek
- May 15 and May 18 is Montview and Old Fish Creek Falls Road
- Saturday, May 16 is Amethyst
- TBD is 12th Street and Shield Drive
- TBD is the Transit Center Parking Lot
Paving Schedule
- May 18-19 is Ridge Road
- May 19-20 is Storm Meadows Drive
- May 20-22 is Burgess Creek.
- May 26 is Montview and Trollhaugen
- May 28 is 12th Street and Shield Drive
- TBD, Old Fish Creek Falls Road
- June 2 is the Transit Center Parking Lot
- June 6 is Amethyst